Completion of first expansion phase of EGGER’s “Europe Plant” in Wismar (GER): MDF, flooring and lamination
Eleven months after the cutting of the first turf, the first expansion phase was successfully concluded in Wismar with the commencement of lamination activities, and MDF and flooring production.
| 24.081999 |
1st board was pressed on the Wemhöhner short-cycle press |
| 13.09.1999 |
1st flooring panel was produced on the world's fastest flooring plant |
| 15.10.1999 |
1st MDF board is leaving the Siempelkamp installation |
| 30.11.1999 |
1st board was pressed on the Hymmen I continuous lamination line |
|
|